In place upgrade from Lync 2013 to Skype for Business 2015

Prerequisites :- Please note that, this article is based on Lync 2013 Enterprise version upgrade on Windows 2008 R2 SP1. If you are using Lync 2013 on Windows 2012 then steps may be different.
1. Make sure that you have the latest CU installed on Lync 2013
2. Update SQL Express edition on all FE servers to SQL 2012 SP2, you can follow the article http://ucserver.blogspot.in/2015/07/update-sql-express-2012-with-service.html
3. Download and install 'KB2533623' https://support.microsoft.com/en-us/kb/2533623
4. Make sure you are using PowerShell version 6.2.9200.0 or later – if not then please download and install latest one.

Publish Topology
1. Install Skype for business Binaries and admin tools on a member server
2. Download corrupt topology from the the member server by using S4B topology builder
3. Right click on the pool which you want to do in place upgrade and choose ‘Upgrade to Skype for Business Server 2015..”
clip_image002
4. Click on ‘yes’
clip_image004
5. You can se the pool is been disappeared from Lync 2013 section
clip_image006
6. Make sure that the pool is visible under Skype section
clip_image008
7. Click on next
clip_image010.
8. Next to continue..
clip_image012
9. Wait..
clip_image014
10. Review the log and click on ‘Finish’ once done.
clip_image016
Run upgrade on servers
1. Make sure that Lync services are in stopped state on FE servers in the pool where you are going do the update Run ‘Stop-CswindowsService’ all servers in the pool to stop the service
clip_image002[5]
2. Mount the media and launch installation
clip_image004[5]
3. You can see C++ 2013 is getting installed..
clip_image006[5]
4. Select ‘Don’t check for updates right now’ [if you are running offline] and click on next
clip_image008[5]
5. Accept the agreement and click on OK
clip_image010[5]
6. You case the installation started, sit back and wait J it may take lot of time..
clip_image012[5]
7. It may prompt for restarts, if it prompts then reboot by clicking on OK
clip_image014[5]
8. Once the installation is done you can see green tick marks J. Click on OK to finish
clip_image016[5]
9. It will remind you that you have to start the pool after installation, click on OK
clip_image018
10. Execute the installation on all other servers in the pool
11. Once the update is done on all servers then run ‘Start-CsPool –PoolFqdn <pool name>’ command on a FE server and make sure that the services are up on all servers.
clip_image002[7]
clip_image004[7]
Please note that ‘Start-CsPool’ new command introduced in S4B 2015 and by running this command you can start services on all servers in this pool.